HMA-FO Progress Task 4  1004

  • This progress report covers the activities performed in April 2010.

Project Manager Assessment

  • The status of the project is nominal.

Key Problem List

  • None

Deliverables Table

  • OSEOP Charter
  • OGC 06-141 V0.9.4 
  • OGC 06-141 V0.9.5 draft 1 
  • OGC 06-141 V0.9.5 draft 2 
  • OGC 06-141 V0.9.5 draft 3
  • SOFTWARE DEVELOPMENT PLAN FOR HMA FOLLOW ON TASK 4 – ORDER (SDP)
  • SOFTWARE PRODUCT ASSURANCE PLAN FOR HMA FOLLOW ON (SPAP)
  • OPGW SOFTWARE REQUIREMENTS SPECIFICATION DOCUMENT (SRS)
  • OPGW SOFTWARE DESIGN DOCUMENT (SDD)
  • IMPROVEMENT OF SCENE SELECTION OPTIONS HANDLING TECHNICAL NOTE V1.0
  • IMPROVEMENT OF ORDERING OPTIONS HANDLING TECHNICAL NOTE

WP-10000: Project Management

Activities performed

  • WP-11000: Technical coordination
    • Preparation and attendance of progress teleconference
    • Management of actions raised at PR:
      • HMA FO PR#11 – Joint teleconf with MDA

Teleconference held on 13/04/2010

      • HMA FO PR#13 – Elsag-Datamat to interact with Olivier Barois to collect the ESA default values.

Teleconference held on 21/04/2010. Clarified the needs for default values for order options.

  • WP-12000: Configuration Management
    • None
  • WP-13000: Quality Assurance
  • WP-14000: OGC TC Meetings Attendance
    • None

Outcome and results

  • Progress Reports
  • Minutes of Meeting

Problems and concerns

  • None

Plans for next period

  • To attend progress teleconf and Ordering SWG teleconf

WP-20000: Engineering

Activities performed

  • WP-21000: Order Server Technical Specification and Architectural Design
    • No further activities performed because the OPGW SRS and SDD have been successfully accepted at PR.
  • WP-22000: HMA Ordering ICD Update
    • On-going preparation of final update of HMA Ordering ICD:
      • Alignment with GML 3.2.1
      • Alignment with SPS/SWE 2.0
      • Add WS-notification
      • And other minor improvements
  • WP-23000 : Order Server Acceptance Test Plan Definition
    • Not started yet
  • WP-24000 : Test Suite Definition (ATS, ETS)
    • Going-on preparation of ETS
  • WP-25000: HMA Ordering ICD contribution (con terra)
    • None

Outcome and results

  • None

 Problems and concerns

  • No major problems

Plans for next period

  • Going on the preparation of final OGC 06-141 V0.9.5.

WP-30000: Implementation and Testing

Activities performed

  • WP-31000: Order Server Design and Development
    • Not started yet
  • WP-32000: SSE Integration Support
    • Not started yet
  • WP-33000: Order Server Acceptance Testing
    • Not started yet
  • WP-34000: Support to Order Server  Acceptance Testing
    • Not started yet

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period  

  • None

 

 

 


Contributors to this page: Daniele Marchionni .

Page last modified on Thursday 27 of May 2010 17:30:12 CEST by Daniele Marchionni.

Category: HMA