HMA-FO Progress Task 4 0910

HMA-FO Progress Task 4  0910

This progress report covers the activities performed in October 2009.

Project Manager Assessment

·        The status of the project is nominal.

Key Problem List

·        None

Deliverables Table

·        OSEOP Charter

·        OGC 06-141 V0.9.4

WP-10000: Project Management

Activities performed

·        WP-11000: Technical coordination (ED)

o   Preparation and attendance to TASK 4 progress teleconference

·        WP-12000: Configuration Management (ED)

o   None

·        WP-13000: Quality Assurance (ED)

o   None

·        WP-14000: OGC TC Meetings Attendance (ED)

Started activities for setting-up the SWG for Ordering Service for Earth Observation Products (OSEOP):

o   Reviewed OGC policies

o   Prepared OSEOP Charter

o   OSEOP Charter internally reviewed

o   Charter sent to OGC on 29/10/2009. Waiting for comments for formally starting the SWG activities.

o   Current list of supporters:

•                 Daniele Marchionni          Elsag Datamat

•                 Uwe Voges          conterra

•                 Pier Giorgio Marchetti     ESA

•                 Michael Schick    EUMETSAT

•                 Gasperi Jerome  CNES

•                 Goor Erwin          VITO

•                 Lucio Colaiacomo             EUSC

Outcome and results

·        OSEOP Charter

·        Coments to Charter

Problems and concerns

·        None

Plans for next period

·        To attend next progress teleconf and prepare progress report for the next reporting period.

·        To attend next teleconf about the SWG activities

WP-20000: Engineering

Activities performed

·        WP-21000: Order Server Technical Specification and Architectural Design (ED)

Not started yet.

·        WP-22000: HMA Ordering ICD Update (ED)

o   Review of OGC 06-141 V0.9.4 and submission of comments to the OGC Issue Tracker set up for OSEOP.

o   Started update of the document on the basis of the issued comments.

·        WP-23000 : Order Server Acceptance Test Plan Definition (ED)

Not started yet.

·        WP-24000 : Test Suite Definition (ATS, ETS) (con terra)

Started preparation of ATS.

Chosen approach: Define test design on scenario basis e.g.:

o   Basic product ordering: GetCapabilities, GetOptions (including EO Product), Submit, GetStatus

o   Product Ordering with quotation: GetCapabilities, GetOptions (including EO Product), GetQuotation, Submit (via quotation id, GetStatus

o   Product Ordering with async notification,

o   and so on

·        WP-25000: HMA Ordering ICD contribution (con terra)

o   Review of the OGC 06-141 V0.9.4 and submission of comments to the OGC Issue Tracker set up for OSEOP based on the experience on the EUMETSAT implementation.

o   Internal review of the OSEOP charter

o   Set-up of Issue Tracker

 

Outcome and results

OGC 06-141 V0.9.4

Problems and concerns

No major problems

Plans for next period

To continue the updates on the OGC 06-141 document.

WP-30000: Implementation and Testing

Activities performed

·        WP-31000: Order Server Design and Development

Not started yet.

·        WP-32000: SSE Integration Support

Not started yet.

·        WP-33000: Order Server Acceptance Testing

Not started yet.

·        WP-34000: Support to Order Server  Acceptance Testing (con terra)

Not started yet.

Outcome and results

None

Problems and concerns

None

Plans for next period

None

 

 