HMA-FO Progress Task 3 1011

Project Manager Assessment

  • The status of the project is nominal.

Key Problem List

  • None

Deliverables Table

  • None

WP1000 Project Management

Activities performed

  • Progress Meeting (and minutes, actions etc)
  • Coordination with subcontractors
  • prepare for AR Phase-1
  • consolidate documents

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • General Project Management work

WP2000 EO Requirements for ODA

Activities performed

  • finalization document: Use Cases applied to WCS 2.0 EO AP TN
  • finalization Design Definition File-Software Design Document v.1.0 (DDF-SDD)
  • finalization Design Justification File-Software Reuse File v.1.0 (DJF-SRF)
  • finalization Technical Specification-Software Requirements Specification v.1.2 (TS-SRS)
  • finalization Requirements Baseline - Software System Specification v1.4 (RB-SSS)
  • finalization Design Justification File-Software Validation Specification v.1.0 (DJF-SVS)
  • finalization Design Justification File-Software Verification Report v.1.0 (DJF-SVR)

Outcome and results

  • Document: Use Cases applied to WCS 2.0 EO AP TN
  • finalized Document: Design Definition File-Software Design Document v.1.0 (DDF-SDD)
  • finalized Document: Design Justification File-Software Reuse File v.1.0 (DJF-SRF)
  • finalized Document: Technical Specification-Software Requirements Specification v.1.2 (TS-SRS)
  • finalized Document: Requirements Baseline - Software System Specification v1.4 (RB-SSS)
  • finalized Document: Design Justification File-Software Validation Specification v.1.0 (DJF-SVS)
  • finalized Document: Design Justification File-Software Verification Report v.1.0 (DJF-SVR)

Problems and concerns

  • None

Plans for next period

  • finalize Design Definition File-Software User Manual (Server) v.1.0 (DDF-SUM)
  • conduct AR Phase-1

WP3000 Towards OpenGIS Standardization

Activities performed

  • WCS 2.0 EO Application Profile (submitted to OGC WCS.SWG)
  • conducted telecons to familiarize WCS.SWG members with WCS 2.0 EO Application Profile concepts
  • continuing updates EO WCS EO AP
  • presentation of WCS 2.0 at ACM-GIS conference

Outcome and results

  • WCS 2.0 EO Application Profile (submitted to OGC WCS.SWG)


Problems and concerns

  • None

Plans for next period

finalize OGC 10-140 OGC Web Coverage Service 2.0 Interface Standard - Earth Observation Application Profile v.0.2.0

WP4000 Software Implementation

Activities performed

  • continued development of MapServer WCS 2.0 extension
    • implementation and unit testing
  • continued developments for WCS EO AP extension
    • implementation and unit testing
  • continue WCS client upgrade
    • Bug fixes to WCS EO AP support
  • perform AR Phase-1 testing
  • created Screen Capture Movie showing testing of WCS 2.0 and WCS EO AP instantiation

Outcome and results

  • upgraded instantiation of WCS 2.0 using MapServer at EOX
  • testing WCS Client developments against WCS 2.0 instantiation at EOX
  • Movie showing testing of components and request for WCS 2.0 and WCS EO AP instantiation

Problems and concerns

  • None

Plans for next period

  • None

WP5000 Software Open Use & Community Support

Activities performed

  • submitted MapServer WCS 2.0 extension to MapServer community
  • submitting patches required for ongoing developments for the new MapServer 6.0 release

Outcome and results

  • WCS 2.0 Extension accepted by MapServer community (MapServer Ticket 3595)
    • extension is included in trunk
    • extension will be included in upcoming MapServer 6.0 release

Problems and concerns

  • None

Plans for next period

  • None