Loading...
 
ESA > Join & Share > HMA > HMA-FO Progress Task 3 1009
Print

HMA-FO Progress Task 3 1009

Project Manager Assessment

  • The status of the project is nominal.

Key Problem List

  • None

Deliverables Table

  • None

WP1000 Project Management

Activities performed

  • Progress Meeting (and minutes, actions etc)
  • Coordination with subcontractors
  • updated the planning for deliverables and implementations (due to delay in WCS and prolonged Requirement phase)

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • General Project Management work
  • Progress Review Meeting

WP2000 EO Requirements for ODA

Activities performed

  • Review of HMA-FO_ODA Requirements Baseline - Software System Specification v1.3
  • update of Use Cases applied to WCS 2.0 EO AP TN

Outcome and results

  • RIDs and comments on RIDs to the HMA-FO_ODA Requirements Baseline - Software System Specification v1.3

Problems and concerns

  • None

Plans for next period

  • finalize HMA-FO_ODA Requirements Baseline documents
  • clarification of the overall concept and use of coverage and its relationship to scene/image/stripe/product

WP3000 Towards OpenGIS Standardization

Activities performed

  • participation at OGC TC Toulouse meeting (EOX)
    • presentation WCS 2.0
    • presentation WCS EO AP
    • presentation GeoTIFF extension
    • presentation GML extension
    • presentation JPEG extension (Joan Maso)
    • presentation NetCDF extension (S.Nativi, B.Domenico, and L. Bigagli)
    • presentation GGIWG (GeoTIFF and JPEG2000) (Emmanuel Devys)


Outcome and results

  • update of draft WCS EO AP
  • update of draft GeoTIFF extension

Problems and concerns

  • None

Plans for next period

  • continue WCS EO AP
  • continue GeoTIFF extension
  • continue to coordinate other extensions

WP4000 Software Implementation

Activities performed

  • continued development of MapServer WCS 2.0 extension
    • implementation and unit testing
  • continued developments for WCS EO AP extension
    • implementation and unit testing
  • continue WCS Client developments
    • finalisation of WCS 2.0 "base" client


Outcome and results

  • upgraded instantiation of WCS 2.0 using MapServer at EOX
  • testing WCS 2.0 Client developments against WCS 2.0 instantiation at EOX

Problems and concerns

  • None

Plans for next period

  • None

WP5000 Software Open Use & Community Support

Activities performed

  • coordination and communication with MapServer community

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • None




Contributors to this page: Christian Schiller .

Page last modified on Tuesday 25 of January 2011 19:54:26 CET by Christian Schiller.

Category: HMA