HMA-FO Progress Task 3 0910

Project Manager Assessment

  • The status of the project is nominal.

Key Problem List

  • None

Deliverables Table

  • None

WP1000 Project Management

Activities performed

  • WP1100: Overall Project Coordination (EOX)
    • all Subcontracts signed and received
  • WP1300: Subcontractor Management
    • Liaison with wrt invoicing procedure
  • WP1600: Project Reporting (EOX)
    • Management Progress report 09/2009 Wiki
    • Management Progress report 10/2009 Wiki

Outcome and results

  • Technical & Organisational Telecon at 2009-10-20
  • Consortium agreed on 3-week interval

Problems and concerns

  • None

Plans for next period

  • Telecon at 2009-11-10

WP2000 EO Requirements for ODA

Activities performed

  • WP2100: EO Data and Service Characteristics (EOX)
    • Experienced quite some problems with EOLI-SA and the login as registered user
    • Problems could finally be solved on 2009-10-30
    • Downloaded first ENVISAT Demo-Dataset
  • WP2200: EO Metadata Requirements (Spot)
    • Started with analysis of relevant metadatasets
  • WP2300: GSC-DA, DAIL, HMA-E Interface Requirements (EOX)
    • Collected relevant documents
    • Analysis of GSC-DA nearly finished
  • WP2400: SSE Client Requirements (GIM)
    • Analysis of potential improvements to WebMapViewer Coverage Download window
  • WP2500: GEOSS & INSPIRE Standards (EOX)
    • Collected relevant documents
  • WP2600: Service Industry Needs (Spot)
    • Start with analyses of Requirements
  • WP2700: Advanced Concepts (WCPS, P2P,Tilinng,...) (JUB)
    • .

Outcome and results

  • No documents so far

Problems and concerns

  • No major problems, access with EOLI-SA cause slight delay

Plans for next period

  • Continue with analysis of requirements
  • Create first draft of RB-Documents

WP3000 Towards OpenGIS Standardization

Activities performed

  • WP3100: WCS 2.0 SWG Liaison (JUB)
    • Regular active participation in weekly OGC WCS telecons, including several times facilitation of telecon;
    • Input to mailing list discussions aiming at clarification of concepts and advancing consensus;
    • Drafting of WCS 2.0 documents for discussion by SWG:
      • GML 3.2.1 Application Schema for WCS (including XML Schema) (OGC 09-146)
      • WCS 2.0 Core (including XML Schema) (OGC 09-110)
      • WCS 2.0 Extension: KVP protocol (OGC 09-147)
  • WP3200: WCS 2.0 SWG Liaison (Spot)
    • Following mailing List discussions
  • WP3300: WCS 2.0 SWG Liaison (EOX)
    • Participation in regular WCS telecon
    • Stephan Meissl become Group member at WCS.SWG, Christian Schiller acts as Proxy
    • Following mailing List discussions
    • Analysis of WCS 2.0 Core draft (OGC 09-110)
    • Analysis of WCS extension - KVP Protocol (OGC 09-147)
  • WP3400: WCS 2.0 SWG Liaison (GIM)
    • Started analysis of WCS 2.0 Core draft (OGC 09-110)
  • WP3500: OGC Interoperability Program (JUB)
    • none
  • WP3600: EO Application Profile Development (JUB)
    • .
  • WP3700: Contribution to EO Application Profile & Conformance Testing (EOX)
    • .
  • WP3800: OGC Conformance Test Approach & Tools (JUB)
    • .
  • WP3900: OGC Conformance Testing & Reporting (JUB)
    • .

Outcome and results

  • Drafted WCS 2.0 documents for discussion by WCS.SWG:
    • GML 3.2.1 Application Schema for WCS (including XML Schema) (OGC 09-146)
    • WCS 2.0 Core (including XML Schema) (OGC 09-110)
    • WCS 2.0 Extension: KVP protocol (OGC 09-147)

Problems and concerns

  • Some diverging discussion within the WCS.SWG which hinders progress (specifications must be completed before Nov 09)

Plans for next period

  • Pushing WCS 2.0 draft documents (OGC 09-110, 09-146, 09-147) further, attempting to make discussions more productive
  • evaluate draft specifications in-house through proofreading and XML schema validation

WP4000 Software Implementation

Activities performed

  • WP4100: WCS Server extension implementation (EOX)
    • Stephan Meissl participated at FOSS4G contacts with many developers of the OpenSource Geo-Community gathered valuable information about performance differences between GeoServer and MapServer
  • WP4200: SSE Client Extension Implementation (GIM)
    • .
  • WP4300: Acceptance Test Planning (EOX)
    • .
  • WP4400: Transfer, Acceptance Testing & Reporting (ECSS) (EOX)
    • .
  • WP4500: WCS Server Warranty (EOX)
    • .
  • WP4600: SSE Client Warranty (GIM)
    • .
  • WP4700: Advanced Concepts - Implementations (JUB)
    • .

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • None

WP5000 Software Open Use & Community Support

Activities performed

  • Stephan Meissl participated at FOSS4G, contacts with many developers of the OpenSource Geo-Community

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • None


Contributors to this page: Christian Schiller .

Page last modified on Friday 06 of November 2009 17:17:57 CET by Christian Schiller.