HMA-FO Progress Task 3 0909
Project Manager Assessment
- The status of the project is nominal.
Key Problem List
- None
Deliverables Table
- Project Management Plan (PMP) "HMA-FO_ODA-PMP-EOX_0.1_20090916
WP1000 Project Management
Activities performed
- WP1100: Overall Project Coordination (EOX)
- Product Management Plan (PMP)
- Technical Meeting_20090918 organized
- Objectives and Outcomes for Task 3 added to HMA-FO Wiki
- WP1200: Contractor Management (EOX)
- Contract negotiation with ESA finalised and Contract signed
- Contracts with sub-contractors finalised and subcontracts signed
- WP1300-WP1500: Subcontractor Management (GIM/JUB/Spot)
- Sub-contracts finalised and signed
- WP1600: Project Reporting (EOX)
- MoMs of Technical Meeting_20090918
- Management Progress report 09/09 Wiki
Outcome and results
- Wiki pages for Task 3 initialised and updated
- Objectives and Outcomes for Task 3 added to HMA-FO Wiki
- Product Management Plan (PMP) delivered
- Setup of project-internal SVN and trac system
Problems and concerns
- None
Plans for next period
- General Project Management work
WP2000 EO Requirements for ODA
Activities performed
- WP2100: EO Data and Service Characteristics (EOX)
- EOX requested CAT-1 User Status to get access to examples of all datasets available at ESA
- WP 2200: EO Metadata Requirements (Spot)
- initiating requirement collection
- WP2300: GSC-DA, DAIL, HMA-E Interface Requirements (EOX)
- Document collection initiated
- WP2400: SSE Client Requirements (GIM)
- Participation to the Technical Meeting on 20090918
- WP2500: GEOSS & INSPIRE Standards (EOX)
- Document collection initiated
- WP 2600: Service Industry Needs (Spot)
- initiating requirement collection
- WP2700: Advanced Concepts (WCPS, P2P,Tilinng,...) (JUB)
- .
Outcome and results
- Accepted as CAT-1 user, but only for ASAR Medium Resolution level 1 products (systematic NRT processing at ESRIN, Kiruna and Matera
Problems and concerns
- tried to clarify access to other products with EO-Help Desk, but so far no answer -> need to upgrade access rights
Plans for next period
- Analyse of EO date requirements
WP3000 Towards OpenGIS Standardization
Activities performed
- WP3100: WCS 2.0 SWG Liaison (JUB)
- participation at OGC TC meeting in Darmstadt (end of September):
- facilitating Coverages.DWG meeting with 3 presentations by JUB
- facilitating WCS.SWG meeting, with emphasis on discussion of WCS 2.0 design issues tabled by JUB
- Regular active participation in weekly OGC WCS telecons, including several times facilitation of telecon;
- Input to mailing list discussions aiming at clarification of concepts and advancing consensus;
- Investigation on status and suitability of GML 3.2.1 by studying documents and exchanging with several GML and SWE proponents
- participation at OGC TC meeting in Darmstadt (end of September):
- WP3200: WCS 2.0 SWG Liaison (Spot)
- Participation to WCS 2.0 SWG meeting at Darmstadt OGC TC Meeting
- WP3300: WCS 2.0 SWG Liaison (EOX)
- OGC Technical Committee meetings participation (Stephan Meissl)
- Contribution to HMA AWG presentations - HMA-FO Task 3
- Contribution to Coverages DWG presentations - HMA-FO Task 3
- Participation at WCS 2.0 SWG meeting
- Participation in weekly WCS Telecon
- WP3400: WCS 2.0 SWG Liaison (GIM)
- Participation to WCS 2.0 SWG meeting at Darmstadt OGC TC Meeting
- WP3500: OGC Interoperability Program (JUB)
- provided input to OWS-7 planning to foster uptake of WCS-related topics
- WP3600: EO Application Profile Development (JUB)
- .
- WP3700: Contribution to EO Application Profile & Conformance Testing (EOX)
- Evaluating the WCS 2.0 Core Draft version
- WP3800: OGC Conformance Test Approach & Tools (JUB)
- .
- WP3900: OGC Conformance Testing & Reporting (JUB)
- .
Outcome and results
- 2 Presentations at OGC Technical Committee meeting (Darmstadt)
- HMA AWG presentation of HMA-FO Task 3
- Coverages DWG presentation of HMA-FO Task 3
- rough concept of the changes to GML required by a WCS 2.0, down to the level of UML models
Problems and concerns
- Some diverging discussion within the WCS.SWG which hinders progress (specifications must be completed before Nov 09)
Plans for next period
- Drafting of WCS 2.0 documents, including pertaining XML schema
WP4000 Software Implementation
Activities performed
- WP4100: WCS Server extension implementation (EOX)
- .
- WP4200: SSE Client Extension Implementation (GIM)
- .
- WP4300: Acceptance Test Planning (EOX)
- .
- WP4400: Transfer, Acceptance Testing & Reporting (ECSS) (EOX)
- .
- WP4500: WCS Server Warranty (EOX)
- .
- WP4600: SSE Client Warranty (GIM)
- .
- WP4700: Advanced Concepts - Implementations (JUB)
- .
Outcome and results
- None
Problems and concerns
- None
Plans for next period
- None
WP5000 Software Open Use & Community Support
Activities performed
- WP5100: Open Source Configuration Management (EOX)
- WP5200: Open Source Community Support (EOX)
- WP5300: HMA Wiki Contributions (EOX)
Outcome and results
- None
Problems and concerns
- None
Plans for next period
- None