HMA-FO Progress Task 2 1102
!Project Manager Assessment
The status of the project is nominal.
Key Problem List
- None
Deliverables Table
- I65.1 HMA-FO-DMS-PMD-PMP01-E-R Project Management Plan. v1.0
- I65.7 HMA-FO-DMS-QMD-PAP01-E-R Project Assurance Plan. v1.0
- I51.2.2 Interface Control Document, I25.2 Specifications:
- OGC 09-001 SWE Service Model. RFC
- OGC 08-094 SWE Common Data Model. RFC
- OGC 09-000 SPS 2.0. RFC
- OGC 07-018 EO Extension for SPS. RFC
- I51.1 HMA-FO-DMS-TEC-URD01-10-E-R Software system specification (SSS). v1.1
- I51.2.1 HMA-FO-DMS-TEC-SRD01-10-E-R Software requirements specification (SRS). v1.1
- I51.3.1 HMA-FO-DMS-VVR-SVS01-10-E-R Software Validation Specification. v1.0
- I51.4.1 HMA-FO-DMS-TEC-SDD01-10-E-R Software Design Document (SDD). v1.0
- I51.4.2 HMA-FO-DMS-TEC-SOM02-11-E-R SF Client Operations Manual v1.1
- I51.4.2 HMA-FO-DMS-TEC-SOM01-10-E-R SF Server Operations Manual v1.1
- I64 SFRE software including source code, object code and executables, COTS etc.
WP1000 Project Management
Activities performed
- Coordination with subcontractors
- Monthly progress reports updated
- Preparation for Final Presentation and demo
Outcome and results
- Ongoing
Problems and concerns
- None
Plans for next period
- General Project Management work
WP 2000: Completion of the SPS Specification
Activities performed
- Final OGC adoption vote successful
Outcome and results
- None
Problems and concerns
- None
Plans for next period
- EO SPS 2.0 and others to be made available on OGC site
WP 3000: Sensor Feasibility Reference Environment
Activities performed
- None
- None
Outcome and results
- None
Problems and concerns
- None
Plans for next period
- Software bug fixes if any. Preparation for Open Source release
WP 4000: EO Extension for SPS 2.0 - Conformance Testing
Activities performed
- CTL development of EO SPS 2.0 Executable Test Suite
Outcome and results
- Final CTL scripts
Problems and concerns
- None
Plans for next period
- Release ETS
WP 5000: Additional Server Environments Demonstration
Activities performed
- None
Outcome and results
- SPOT EO SPS 2.0 Server is finished
Problems and concerns
- None
Plans for next period
- SPOT SPS server bug fixes
WP 6000: Warranty
Activities performed
- None
Outcome and results
- None
Problems and concerns
- None
Plans for next period
- None