HMA-FO Progress Task 2 1009

Project Manager Assessment

The status of the project is nominal.

Key Problem List

  • None

Deliverables Table

  • I65.1 HMA-FO-DMS-PMD-PMP01-E-R Project Management Plan. v1.0
  • I65.7 HMA-FO-DMS-QMD-PAP01-E-R Project Assurance Plan. v1.0
  • I51.2.2 Interface Control Document, I25.2 Specifications:
    • OGC 09-001 SWE Service Model. RFC
    • OGC 08-094 SWE Common Data Model. RFC
    • OGC 09-000 SPS 2.0. RFC
    • OGC 07-018 EO Extension for SPS. RFC
  • I51.1 HMA-FO-DMS-TEC-URD01-10-E-R Software system specification (SSS). v1.1
  • I51.2.1 HMA-FO-DMS-TEC-SRD01-10-E-R Software requirements specification (SRS). v1.1
  • I51.3.1 HMA-FO-DMS-VVR-SVS01-10-E-R Software Validation Specification. v1.0
  • I51.4.1 HMA-FO-DMS-TEC-SDD01-10-E-R Software Design Document (SDD). v1.0

WP1000 Project Management

Activities performed

  • Coordination with subcontractors
  • Coordination of Specification RFC Issues
  • Coordination of SFRE Development

Outcome and results

  • Ongoing

Problems and concerns

  • None

Plans for next period

  • General Project Management work

WP 2000: Completion of the SPS Specification

Activities performed

  • RFC candidate SPS Extension for EO.
  • Comments on SPS 2.0 and SWE specifications are being discussed.

Outcome and results

  • Specification Reviews.

Problems and concerns

  • None

Plans for next period

  • SPS EO Specification RFC comments to be reviewed
  • SPS 2.0 and Swe Common RFC comments to be taken in to docs (or rejected)

WP 3000: Sensor Feasibility Reference Environment

Activities performed

  • Development work on SF Client and SF Server
  • Editing SVS (Software Validation Specification) document

Outcome and results

  • Software updated, dev versions released and tested together

Problems and concerns

  • None

Plans for next period

  • Software development
  • Editing of Validation Spec

WP 4000: EO Extension for SPS 2.0 - Conformance Testing

Activities performed

  • Downloaded and set up TEAM engine
  • CTL development of EO SPS 2.0 Executable Test Suite

Outcome and results

  • Draft CTL scripts

Problems and concerns

  • None

Plans for next period

  • Continue development of ETS

WP 5000: Additional Server Environments Demonstration

Activities performed

  • SPOT Development of EO SPS 2.0 Server

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • Continue development

WP 6000: Warranty

Activities performed

  • None

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • None