Project Manager Assessment

The status of the project is nominal.

Key Problem List

  • None

Deliverables Table

  • I65.1 HMA-FO-DMS-PMD-PMP01-E-R Project Management Plan. v1.0
  • I65.7 HMA-FO-DMS-QMD-PAP01-E-R Project Assurance Plan. v1.0
  • I51.2.2 Interface Control Document, I25.2 Specifications:
    • OGC 09-001 SWE Service Model. RFC
    • OGC 08-094 SWE Common Data Model. RFC
    • OGC 09-000 SPS 2.0. RFC
    • OGC 07-018 EO Extension for SPS. RFC
  • I51.1 HMA-FO-DMS-TEC-URD01-10-E-R Software system specification (SSS). v1.1
  • I51.2.1 HMA-FO-DMS-TEC-SRD01-10-E-R Software requirements specification (SRS). v1.1
  • I51.3.1 HMA-FO-DMS-TEC-ATP01-10-E-R Acceptance Test Plan. Draft, being converted to ECSS SVP format.
  • I51.4.1 HMA-FO-DMS-TEC-SDD01-10-E-R Software Design Document (SDD). v1.0

WP1000 Project Management

Activities performed

  • Progress meeting (and minutes, actions etc)
  • Coordination with subcontractors
  • Progress report updated
  • Coordination of EO Extension for SPS RFC

Outcome and results

  • Ongoing

Problems and concerns

  • None

Plans for next period

  • General Project Management work

WP 2000: Completion of the SPS Specification

Activities performed

  • RFC candidate SPS Extension for EO.
  • Comments on SPS 2.0 and SWE specifications are being discussed.

Outcome and results

  • Specification Reviews.

Problems and concerns

  • SPS 2.0 will need to be revised to match OGC Specification Model more closely. Need to ensure this is done in a timely fashion.

Plans for next period

  • SPS EO Specification RFC comments to be received
  • SPS 2.0 and Swe Common RFC comments to be taken in to docs (or rejected)

WP 3000: Sensor Feasibility Reference Environment

Activities performed

  • Development work on SF Client and SF Server
  • Drafting validation specification document
  • Released v1.0 of SDD

Outcome and results

  • Internal release 2 of SF Server and SF Client

Problems and concerns

  • None

Plans for next period

  • Test and demonstrate internal release 2 SF Client (first UI) and SF Server
  • Architecture document review
  • Drafting of Validation Spec

WP 4000: EO Extension for SPS 2.0 - Conformance Testing

Activities performed

  • Discussion of suitable conformance classes for SPS specifications and level of detail in SPS ATS
  • Investigation of different TEAM engine options

Outcome and results

  • None (awaiting updates/consolidation of TEAM Engine)

Problems and concerns

  • TEAM engine situation complicated. Several versions exist.

Plans for next period

  • Get info from various partners to say which TEAM engine version to use
  • Begin development of ETS, based on ATS for EO Extension for SPS in RFC candidate

WP 5000: Additional Server Environments Demonstration

Activities performed

  • None

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • None

WP 6000: Warranty

Activities performed

  • None

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • None