HMA-FO Progress Task 2 1002

Project Manager Assessment

The status of the project is nominal.

Key Problem List

  • None

Deliverables Table

  • I65.1 HMA-FO-DMS-PMD-PMP01-E-R Project Management Plan. v1.0
  • I65.7 HMA-FO-DMS-QMD-PAP01-E-R Project Assurance Plan. v1.0
  • I51.2.2 Interface Control Document, I25.2 Specifications:
    • OGC 09-001 SWE Service Model, OGC 08-094 SWE Common Data Model. RFC
    • OGC 09-000 SPS 2.0, OGC 07-018 SPS for EO Application Extension. Draft
  • I51.1 HMA-FO-DMS-TEC-URD01-10-E-R Software system specification (SSS). v1.0
  • I51.2.1 HMA-FO-DMS-TEC-SRD01-10-E-R Software requirements specification (SRS). v1.0


..............

WP1000 Project Management

Activities performed

  • Progress Meeting (and minutes, actions etc)
  • Coordination with subcontractors
  • Progress report updated
  • Progress Review and HMA AWG Meetings

Outcome and results

  • Ongoing

Problems and concerns

  • None

Plans for next period

  • General Project Management work


WP 2000: Completion of the SPS Specification

Activities performed

  • Ongoing work on SPS Extension for EO. Formalising requirements and ATS.
  • Drafts of SPS 2.0 and SWE specifications delivered for RFC

Outcome and results

  • Draft Specifications. Waiting for comments from OAB. Have informal feedback that SPS 2.0 will need to be revised to match OGC Specification Model more closely

Problems and concerns

  • None

Plans for next period

  • SPS EO Specification completion (agreed to be handled as part of SPS 2.0 WG)
  • respond to any SPS 2.0 and Swe Common comments, including SPS 2.0 revision.
  • SPS SWG meeting at Frascati (iGSI, SPOT in person, DEIMOS by teleconference)

WP 3000: Sensor Feasibility Reference Environment

Activities performed

  • Updates of documents to the formats of newer ECSS-E-ST-40C. RBD to SSS and SRD to SRS.
  • Other minor RIDs in PR Minutes addressed
  • Development meeting in Toulouse 25-26 February.

Outcome and results

  • Revised SSS and SRS documents

Problems and concerns

  • None

Plans for next period

  • Finalise and re-deliver SSS and SRS documents
  • Draft architecture documents

WP 4000: SPS App. Profile for EO - Conformance Testing

Activities performed

  • Discussion of suitable conformance classes for SPS specifications and level of detail in SPS ATS

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • Revise ATS for SPS following updates to OGC Specification Model
  • Finalise ATS for SPS EO

WP 5000: Additional Server Environments Demonstration

Activities performed

  • None

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • None

WP 6000: Warranty

Activities performed

  • None

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • None