HMA-FO Progress Task 2 0911

!Project Manager Assessment

The status of the project is nominal.

Key Problem List

  • None

Deliverables Table

  • I65.1 HMA-FO-DMS-PMD-PMP01-E-R Project Management Plan
  • I65.7 HMA-FO-DMS-QMD-PAP01-E-R Project Assurance Plan

WP1000 Project Management

Activities performed

  • Progress Meeting (and minutes, actions etc)
* Coordination with subcontractors
  • Progress report updated
* Preparation for Progress Meeting

Outcome and results

  • Ongoing

Problems and concerns

  • None.

Plans for next period

  • General Project Management work

WP 2000: Completion of the SPS Specification

Activities performed

  • Ongoing SweCommon and SPS and O&M discussions.
  •  OWS Common 1.2 feedback (accepted after JolyonMArtin submitted as ESA CRs)
* Drafts of SPS 2.0 and SWE specifications ready for TC at Mountaing View OGC meeting

!!!Outcome and results

  • Draft Specifications. Receiving final comments and ready for TC.

!!!Problems and concerns

  • None

Plans for next period

  • SPS EO Specification completion.
  • TC at Mountain View to (hopefully) propose SPS 2.0 and Swe Common go to formal RFC, and that SPS EO Profile can be handled by SPS 2.0 WG 

WP 3000: Sensor Feasibility Reference Environment

Activities performed

* Review of RBD by Astrium regarding Client

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • Work on RBD together, to refine it alongside specifications and high level requirements

WP 4000: SPS App. Profile for EO - Conformance Testing

Activities performed

* Discussion of suitable conformance classes for SPS specifications and level of detail in SPS ATS 

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • Review of ATS for SPS and creation for SPS EO

WP 5000: Additional Server Environments Demonstration

Activities performed

  • None

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • None

WP 6000: Warranty

Activities performed

  • None

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • None

 

 

 