ERGO PROGRESS 0907 INTECS
ERGO Progress July 2009: Intecs
No input from GeoCat has been received so far. According to the informal progress report received by email middle of July the following services have been developed
- Services ready for testing:
- GetRecordById
- GetRepositoryItem
- DescribeRecord
The following Services are under developement
- Services that we are working to finish:
- GetRecords
- GetCapabilities
Anyway no code or access to these services have been provided to Intecs. Thus the testing activities for the GeoNetwork have not been starte
Missing deliverable from GeoCat. The CDR has not been closed and payment is not authorized for GeoCat .
ID | Risk Title | Severity | Likelihood | Risk Index | Risk Domain | Action and status |
1 | Availability of HMA-T testing guidelines | 3 | 3 | 9 | Schedule | Monitor HMA-T progress reports |
2 | CIM extension package availability | 3 | 3 | 9 | Schedule and Cost |
Monitorthe extension package status and discuss with F.H. |
As agreed with ESA the ATS will be based on the HMA-T ATS. The ATS for the CIM and the CIM extension has been received from HMA-T. The CTL scripts have been started in HMA-T. Intecs contributed to the CTL development in order to generalize the binding.
The following documents have been delivered:
- None
Activities performed
- GeoNetwork has been contacted in order to discuss the planning. Currently no feedback has been received regarding a possible date for the code delivery and for the availability of an installation package.
- Management of OGC SVN. Some account has been created and some people have been added to the HMA project. The main structure of the repository has been created. The template for the EOP CTL has been uploaded in the main trunk.
Outcomes and results
- None
Problems and concerns
- See "key problem list" and "risks" ections.
Plans for next period
- New planning to be discussed with ESA as soon as feedback from Geo
- CDR closure for GeoCat
Quality Activities performed
- Internal quality control activity of the SW development
- Internal quality control activity on the testing and SPR generation.
Quality Activities Plans for next period
- Internal quality control activity on the testing, SPR generation and SW development will be delivered during the next period.
Activities performed
- none.
Outcomes and results
- none.
Problems and concerns
- none.
Plans for next period
- This WP has been completed
Activities performed
- Bug fixing.
Outcomes and results
- none.
Problems and concerns
- none.
Plans for next period
- none
Activities performed
- The CTL for EO has been updated. A new generic structure has been defined. Tis structure allow performing all the test with different binding (e.g. implementation only supporting SOAp can perform all the tests. This was not possible in the ATS definition where only one test was related to SOAP)
- The new structure has been sent as input to HMA-T in order to extend it and use it for both EO and CIM profiles.
- The test of the EbRR has been continued.
Outcomes and results
- None
Problems and concerns
- None
Plans for next period
- EbRR CTL development will be continued
- Start of ctl developemtn for GeoNetwork
- The testing and SPR generation will be continued.