ERGO PROGRESS 0906 INTECS
ERGO Progress June 2009: Intecs (TO BE COMPLETED)
A second meeting has been held the 11th of June to close the CDR. The Intecs and 4CT deliverables have been accepted. Thus Intecs and 4CT can submit the invoice on EFIS. GeoCat has some delay and will deliver the code and the document by the 10th of July. After the delivery and the acceptance from ESA GeoCat will be authorized to submit the invoice.
It has been agreed to have a unique AR in september (date to be confirmed)
Missing deliverable from GeoCat. The CDR has not been closed and payment is not authorized for GeoCat .
ID | Risk Title | Severity | Likelihood | Risk Index | Risk Domain | Action and status |
1 | Availability of HMA-T testing guidelines | 3 | 3 | 9 | Schedule | Monitor HMA-T progress reports |
2 | CIM extension package availability | 3 | 3 | 9 | Schedule and Cost |
Monitorthe extension package status and discuss with F.H. |
As agreed with ESA the ATS will be based on the HMA-T ATS. The ATS for the EOP has been finalized. The ATS for the CIM and the CIM extension package will be delivered later due to missing input from HMA-T.
The following documents have been delivered:
GEONETWORK OPENSOURCE SOFTWARE Acceptance Test Plan - ERG-GEON-4100-INT, issue 1.1, date 10/06/2009
- TOOLBOX SOFTWARE Acceptance Test Plan - ERG-ATP-4100-INT , issue 1.1, date 08/06/2009
Activities performed
- A meeting to close the CDR has been prepared and held (11/06/09)
- The new CDR documentation has been reviewed
- Some bug fixiThe TEAM Engine has been merged with the latest version of the code on the OGC SVN (to integrate the engine with the manager)
- The manager has been succesfully installed and the code has been sent to the SSE operational team for the installation in ESA
- Invoices have been submitted.
Outcomes and results
- Invoices on EFIS
Problems and concerns
- See "key problem list" and "risks" ections.
Plans for next period
- CDR closure for GeoCat
- Some RIDs on the CDR Documentation have been analyzed.
-
Internal quality control activity of the CDR Closure Documentation, with reference to document RIDs.
-
Added CDR documentation in the delivery site.
Quality Activities Plans for next period
- Internal quality control activity on the new issue of the ERGO documentation will be delivered during the next period.
Activities performed
- none.
Outcomes and results
- none.
Problems and concerns
- none.
Plans for next period
- This WP has been completed
Activities performed
- Toolbox implementation of the catalogue is tested against the new ATP.
- Bugs found and fixed when needed.
Outcomes and results
- none.
Problems and concerns
- none.
Plans for next period
- none
Activities performed
- The ATP for GeoNetwork has been redefined and delivered to ESA.
- The CTL has been further developed.
- The Toolbox ATP has been finalized and delivered to ESA.
- Tehs in the EbRR has been continued. Total bugs found 26 bugs. 20 bugs fixed, 6 still pending.
Outcomes and results
- GEONETWORK OPENSOURCE SOFTWARE Acceptance Test Plan - ERG-GEON-4100-INT, issue 1.1, date 10/06/2009
- TOOLBOX SOFTWARE Acceptance Test Plan - ERG-ATP-4100-INT , issue 1.1, date 08/06/2009
Problems and concerns
- None
Plans for next period
- EbRR CTL development will be continued
- Start of ctl developemtn for GeoNetwork
- The testing and SPR generation will be continued.