ERGO Progress May 2009: Intecs

Project Manager Assessment

 

The CDR meeting has been prepared and held the 8th of May.The CDR has not been closed. The ATP documentation has not been accepted.  A progress meeting (Intecs+ESA) has been done to discuss the steps for the CDR closure. Intecs proposed to deliver part of the documentation immediately and the remaining documentation (depending on the HMA-T ATS) two weeks after the ATS delivery. A new payment plan for the CDR is discussed and agreed (50% immediately after the first delivery and 50% qat CDR closure). Deliverable update from GeoCat is late (including the code). Thus the CDR cannot be closed. No feedback from GeoCat regarding the possible documentation and code availability.

The AR has been moved to the end of June to allow Intecs to finalize the tests based on HMA-T input.

 

Key Problem List 

Missing deliverable from GeoCat. if the deliverable will not arrive beginnig of June the CDR for GeoCat cannot be closed and the AR has to be moved ahead (thus splitting again the planning).


Risk Table
ID Risk Title Severity Likelihood Risk Index Risk Domain Action and status
1 Availability of HMA-T testing guidelines 3 3 9 Schedule Monitor HMA-T progress reports
2 CIM extension package availability 3 3 9 Schedule and Cost

Monitorthe extension package status and discuss with F.H.

 

As agreed with ESA the ATS will be based on the HMA-T ATS. The ATS for the EOP has been finalized. The ATS for the CIM and the CIM extension package will be delivered beginning of June. Intecs will be able to close the CDR two week after.

Deliverables List

The following documents have been delivered:

  • ERGO-PMP-1000-INT, Project Management Plan, Issue 1, revision 3, 30/04/2009
  • ERG-ADD-3100-INT, EbRIM implementation with GeoNetwork and OMAR, Toolbox Architectural Design Document, Issue 1, revision 2, 30/04/2009 (Clean document no revisions)
  • ERGO-ebRR-ADD-4CT, ERGO ebRR Architectural design Document, issue 1, revision 0, 24/04/2009
  • ERG-SRD-2100-INT, ERGO Toolbox Software requirement Document, issue 1, revision 2, 30/04/09
  • ERG-SUM-3100-INT, ERGO Toolbox Software User Manual, issue 1, Revision 0, 30/04/09.
WP1000: Project Management


Activities performed 

  • The CDR has been prepared and held (08/05/09)
  • The CDR documentation has been reviewed and the RIDs have been sent to the partners.
  • The RIDs have been discussed during the CDR and the documentation has bee issued again.
  • The new version of the documents has been reviewed and delivered to ESA.
  • A new planning has been agreed with ESA (CDR closure beginning of June, AR beginning of July)
  • The TEAM Engine has been merged with the latest version of the code on the OGC SVN (to integrate the engine with the manager)
  • The manager has been succesfully installed and the code has been sent to the SSE operational team for the installation in ESA
  • Some support has been provided to the CNR and SSE Opetaiona team for the Team Engine installation.
  • The Team Engine has been further tested (during the first part of the buddata validation). Some bugs have been identified and fixed.
  •  

Outcomes and results

  • ERGO-ebRR-ADD-4CT, ERGO ebRR Architectural Design Document, issue 1, revision 1
  • ERGO-ebRR-SUM-4CT, ERGO ebRR Software Installation and User Manual, issue 1, revision 1


Problems and concerns

  • See "key problem list" and "risks" ections.


Plans for next period

  • CDR closure
  • The TEAM Engie code will be further tested.

 

Quality Activities performed

  • Some RIDs on the CDR Documentation have been analyzed.
  • Internal quality control activity of the CDR Documentation, with reference to document RIDs.
  • Added CDR documentation in the delivery site.

 

Quality Activities Plans for next period

  • Internal quality control activity on the new issue of the ERGO documentation will be delivered during the next period.

 

 

WP2100: Requirement definition


Activities performed

  • none.


Outcomes and results

  • none.


Problems and concerns

  • none.


Plans for next period

  • This WP has been completed

 

WP3100 Integration of the OMAR open source implementation in the SSE Toolbox


Activities performed

  • The ADD has been reviewed and updated taking into account the RIDs from ESA
  • Started testing of Toolbox using ebRR ATP. This allowed to check the integration and discover bugs in APIs


Outcomes and results

  • ERG-ADD-3100-INT, EbRIM implementation with GeoNetwork and OMAR, Toolbox Architectural Design Document, Issue 1, revision 3, 22/05/2009

Problems and concerns

  • none.


Plans for next period

  • none

 

WP4100 Validation and Conformance testing


Activities performedThe ATP for

  • The ATP for the buddata ebRR (EOP profile) has been completely redefined and delivered to ESA. The ATP includes tests from the HMA-T ATS (Annex A) test covering requirements defined in Annex G of the specification, some tests for the basic CSW testing and additional tests for the ERGO specific requirements.
  • A first version of tghe CTL scripts has been developed and included in the ATP (Annex) for reference.
  • The update of the Toolbox ATP has been started.
  • Installed and started testing of ebRR. Found 23 bugs.  20 bugs fixed, 3 still pending.

Outcomes and results

  • ERGO-EBRR-ATP-4100-INT, ebRR Acceptance Test Plan, issue 1, revision 1, 25/05/09

 

Problems and concerns

  • None


Plans for next period

  • The ERG-GEON-ATP-4100-INT, GeoNetwork Acceptance Test Plan will be updated and aligned with the ERGO-EBRR-ATP-4100-INT structure.
  • ERG-ATP-4100-INT, Toolbox Acceptance Test Plan will be updated and aligned with the ERGO-EBRR-ATP-4100-INT structure
  • The CTL development will be continued
  • The testing and SPR generation will be continued.

 