ERGO PROGRESS 0812 INTECS
ERGO Progress December 2008: Intecs
The Project Management plan has been updated according to the new plan proposed at the PM3.
The following meeting schedule has been agreed with ESA and the partners. The exact date meeting may change to optimize travels.
Milestone
|
Name
|
Location
|
Major Deliverables
|
Time
|
M1-KO
|
Kick-off
|
ESRIN
|
Project Management Plan
Product Assurance Plan
|
1 April 2008
|
M2-PDR
|
Preliminary Design Review
|
Intecs
|
Requirement Baseline Document
|
23 May 2008
|
M3–CDR 4CT - INT
|
Critical Design Review (EbRR & Toolbox)
|
Foresee technologies
|
Un-validate software
|
13 February 2009
|
M4-AR 4CT – INT
|
Acceptance Review(EbRR & Toolbox)
|
Intecs
|
Architectural Design document
Acceptance Test Document(s)
Validated software
|
16 March 2009
|
M5–CDR GeoC
|
Critical Design Review (GeoNetwork)
|
Intecs
|
Un-validate software
|
16 March 2009
|
GeoCat B.V.
|
Architectural Design document
Acceptance Test Document(s)
Validated software
|
7 April 2009
|
||
M7–FP
|
Final Presentation
|
ESRIN
|
Project Executive Summary
|
30 April 2009
|
- None
ID | Risk Title | Severity | Likelihood | Risk Index | Risk Domain | Action and status |
1 | - | - | - | - | - | - |
2 | - | - | - | - | - | - |
The following documents have been delivered:
- none
Activities performed
- The PMP has been updated according to the new plan
- A template for the ADD has been prepared and sent to the partners.
- A first version of the EbRR ADD has been received anc checked. Some internal RIDs have been sent to 4CT
Outcomes and results
- New project plan.
Problems and concerns
- none.
Plans for next period
- A PM will be prepared and held
- review of the partners ADD
Activities performed
- This WP has been completed.
Outcomes and results
- none.
Problems and concerns
- none.
Plans for next period
- This WP has been completed
Activities performed
- Finalized handling logic for catalogue services.
- Started integrating ebRR code into Toolbox.
- A new plugin has been created for providing catalogue interfaces.
- A new plugin has been created for providing ebRR specific scripting tags.
- The development of the standalone catalogue service has been started.
Outcomes and results
- none.
Problems and concerns
- none.
Plans for next period
- Link to the ebRR catalogue will be finalized.
- ebRR catalogue will be integrated into Toolbox, moving the connection between network based to Java call based.
Activities performed
- The preparation of the validation test documentation has been started (for the EbRR and Toolbox)
Outcomes and results
- none.
Problems and concerns
- none.
Plans for next period
- The work on the documentation will be continued
- The test scripts will be prepared